New AACE-PSP Dumps, AACE-PSP Reliable Exam Simulations
Probably you’ve never imagined that preparing for your upcoming certification AACE-PSP could be easy. The good news is that LatestCram’s dumps have made it so! The brilliant certification exam AACE-PSP is the product created by those professionals who have extensive experience of designing exam study material. These professionals have deep exposure of the test candidates’ problems and requirements hence our AACE-PSP cater to your need beyond your expectations.
To earn the AACE-PSP certification, candidates must meet a rigorous set of requirements. They must have a minimum of three years of professional experience in project planning and scheduling, complete a 150-question exam, and pass a comprehensive review process conducted by a board of peers. AACE-PSP Exam consists of questions on various topics, including planning, scheduling, progress monitoring, cost management, and risk management.
>> New AACE-PSP Dumps <<
100% Pass 2025 AACE-PSP: Planning & Scheduling Professional (PSP) Exam –Reliable New Dumps
In the process of using our AACE-PSP Study Materials if the clients encounter the difficulties, the obstacles and the doubts they could contact our online customer service staff in the whole day. If the clients fail in the test by accident we will refund them at once in the first moment. Our service team will update the AACE-PSP study materials periodically and provide one-year free update. We only use the certificated experts and published authors to compile our study materials and our products boost the practice test software to test the clients’ ability to answer the questions. The clients can firstly be familiar with our products in detail and then make their decisions to buy it or not.
AACE International Planning & Scheduling Professional (PSP) Exam Sample Questions (Q13-Q18):
NEW QUESTION # 13
Which of the following is NOT required when performing weekly or monthly schedule updates?
- A. Original duration of activities.
- B. Percent complete.
- C. Actual finish of activities.
- D. Remaining duration of activities.
Answer: D
Â
NEW QUESTION # 14
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

- A. Delay manufacturing by 5 days.
- B. Delay product release by 5 days.
- C. Expedite packaging by 5 days.
- D. Expedite printing by 5 days.
Answer: B
Â
NEW QUESTION # 15
How much Total Float does drafting the product manual have?

- A. 15 workdays.
- B. 10 workdays.
- C. 0 workdays.
- D. 5 workdays.
Answer: B
Â
NEW QUESTION # 16
SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?
- A. The distance of SUBCO to your project
- B. Pending negotiations with GOUGE.
- C. BILCO liquidated damages in the SDOT contract
- D. SUBCO direct labor and equipment rates
Answer: D
Â
NEW QUESTION # 17
Determine the correct formula and date for the late finish for Activity 9004.

- A. LS.10002 + 1 day -> 11-29-03.
- B. LS.10002 - Lag.7 - l day -> 11-20-03.
- C. LS.10002 - 1 day -> 11-27-03.
- D. LS.10002